打膠機(jī)自動(dòng)打膠的基本過程
一般情況下,打膠機(jī)是中空玻璃自動(dòng)生產(chǎn)線上的后一個(gè)環(huán)節(jié)。一般在壓合段的后面,它是對已經(jīng)組裝和壓合好的中空玻璃進(jìn)行打膠。
濟(jì)南雙組份打膠機(jī)廠家為解說基本次序,如下:
Generally, the glue applicator is the last link in the automatic production line of insulating glass. Generally, it is behind the pressing section, which is used to glue the assembled and pressed insulating glass. Jinan two-component sealant manufacturer explains the basic sequence as follows:
(1)未打膠的玻璃由前面連接的單元送入,當(dāng)玻璃到達(dá)測量裝置時(shí)停止輸送。
(1) The unglued glass is fed into the front connected unit, and the glass is stopped when it reaches the measuring device.
(2)測量總寬度W,并根據(jù)手工輸入的g1和g2值計(jì)算出打膠寬度。W-g1-g2=b
(2) Measure the total width W, and calculate the gluing width according to the manually entered g1 and g2 values. W-g1-g2=b
(3)測量完畢后,玻璃進(jìn)入吸盤吸附區(qū)停止吸盤伸出完全吸附后吸盤與輸送帶同步向打膠區(qū)輸送。
(3) After the measurement is completed, the glass enters the suction cup adsorption area and stops the suction cup stretching out for complete adsorption. After that, the suction cup and the conveyor belt are transported to the glue area synchronously.
(4)當(dāng)玻璃尾邊到達(dá)槍頭時(shí),停止傳送,進(jìn)行定位后,升降機(jī)構(gòu)上升開始進(jìn)行一邊打膠。
(4) When the tail edge of the glass reaches the gun head, stop the transmission. After positioning, the lifting mechanism rises and starts to apply glue at the same time.
(5)當(dāng)上升到玻璃上邊緣時(shí),由測量機(jī)構(gòu)測量玻璃的高度H值,槍頭翻轉(zhuǎn)90度、下支撐就翻上、槍頭位、角注膠后,玻璃開始反向輸送,對上邊(二邊)進(jìn)行打膠。
(5) When it rises to the upper edge of the glass, the measuring mechanism measures the height H value of the glass. After the gun head is turned 90 degrees, the lower support is turned up, and the gun head is positioned and the corner is filled with glue, the glass starts to be transported in reverse, and the upper (two sides) are filled with glue.
(6)當(dāng)按測量好的長度輸送完畢,打完上邊后,槍頭翻轉(zhuǎn)90度、就位、角注膠后。槍頭向下運(yùn)動(dòng),對第三邊進(jìn)行打膠。
(6) When the conveying is completed according to the measured length, and the upper edge is drilled, the gun head is turned 90 degrees, in place, and the corner is filled with glue. The gun head moves downward to apply glue to the third side.
(7)槍頭到達(dá)底邊后翻轉(zhuǎn)90度、就位、角注膠。玻璃向前輸送,對底邊(第四邊)進(jìn)行打膠,并按測量好的長度值運(yùn)動(dòng)。進(jìn)行第四角注膠。完成打膠。
(7) Turn the gun head 90 degrees after reaching the bottom edge, put it in place, and inject glue into the corner. The glass is transported forward, the bottom (fourth side) is glued and moved according to the measured length value. Carry out glue injection for the fourth corner. Complete glue application.
(8)打膠完畢后,吸盤脫離并返回原來區(qū)域,玻璃繼續(xù)向前移動(dòng)。到達(dá)輸送段后延時(shí)停止。由人工取下打好膠的玻璃。下一片玻璃進(jìn)入打膠區(qū),開始下一個(gè)循環(huán)。
(8) After the glue is applied, the suction cup will disengage and return to the original area, and the glass will continue to move forward. It stops after reaching the conveying section. Remove the glued glass manually. The next piece of glass enters the glue area and starts the next cycle.
所有的控制操作由放置在機(jī)器正前面的控制電腦來完成,其界面應(yīng)完成所有操作并進(jìn)行參數(shù)設(shè)置和數(shù)據(jù)調(diào)整,并有自動(dòng)故障診斷功能,適時(shí)顯示狀態(tài)和有關(guān)數(shù)據(jù)。更多相關(guān)內(nèi)容您可以來我們這里
http://dejiansw.cn咨詢了解!
All control operations shall be completed by the control computer placed in the front of the machine. Its interface shall complete all operations and carry out parameter setting and data adjustment. It shall also have the automatic fault diagnosis function to display the status and relevant data timely. You can come to us for more information http://dejiansw.cn Ask about it!
上一篇:打膠機(jī)設(shè)備平常使用中要進(jìn)行定期檢查
下一篇:打膠機(jī)的操作了解五方面要點(diǎn)